After months of underground preparations, including earthworks, tanking, plumbing and retaining, we are out of the ground on the Remanufacturing Facility in Perth for Hitachi Construction Machinery Australia. 90% of the steel and 60% of Tilt panels on the main structure are now standing with external PT slabs continuing to be prepared.

In the background, the projects team at icubed, with builder ADCO, are continuing to coordinate the cranes, specialist booths, oil, air and water reticulation, electrical and mechanical shop drawings and the extensive fit-out equipment to stay on program.

In addition to icubed’s full time Site Representative Sarah Greinke monitoring daily activities, CCTV footage is streamed live to the icubed Project Management Team in Brisbane.

          

 

 